        I. GENERAL INFORMATION 
        Product #2 Epoxy Coating System consists of 
		Product #899 Epoxy Primer followed with two coats 
        of Product #2 High Build Epoxy Floor Coating Epoxy Coating. Product #2 
		High Build Epoxy Floor Coating is available in pigmented finish only.  
        Before installation read Do with epoxies and
		Don't do with epoxies.    
        II. 
        SURFACE PREPARATION 
        Surface Preparation is the most critical portion of any 
        successful resinous flooring system application. All substrates must be properly 
        prepared to a minimum surface profile of CSP-2 as outlined in 
		Epoxy.com Surface Preparation Procedures. Specific attention should be paid to the 
        following:  
        A. Concrete Placement--An efficient vapor barrier should be under 
        slabs on or below grade to prevent moisture migration. A moisture vapor 
        treatment may be necessary.  
        B. Curing and Finishing Techniques of the Concrete 
        Substrate  
        C. Age of Concrete  
        D. Previous Contamination of the Substrate  
        E. 
        Present Condition of the Substrate Also, the temperature and humidity conditions 
        of the area to receive the flooring system should be checked. An optimum room 
        temperature of 75°F with a minimum slab temperature of 60°F is required for 
        proper cure of the resin flooring system.  
        III. MATERIAL QUANTITIES 
        A. Guideline System Requirements for 1000 ft SQ: 21-27 Mils 
		Product #2 High Build Chemical Resistant Epoxy Coating 
		System Qty./ 
        1000 ft°:  
        1. Product #899 Epoxy Primer 4-5 gallons  
        2. Product #2 Chemical Resistant High Build Epoxy Floor Coating Epoxy 
		10-12.5 gallons  
         IV. 
        INSTALLATION  
        A. Product #899 Epoxy Primer  
        1. Mixing  
        a. Stir each component prior to 
        mixing.  
        b. Mix two (2) parts by volume of Part A (Resin) with one (1) part by 
        volume of Part B (Hardener) for three minutes with a low speed electric drill 
        mixing paddle.  
        c. If thinning is desired, add no more than one pint of xylene or 
        MEK per gallon of epoxy at time of mixing.  
        d. Do not mix more material than can 
        be applied in 20-30 minutes. Do not leave 
        mixed material in the pail for longer than 5 minutes or working time will be 
        significantly reduced!  
        2. Application  
        a. Pour mixed resin onto the prepared 
        concrete.  
        b. Spread with either a flat trowel or squeegee, or roller to a coverage of 200 
        to 275 ft sq. per gallon. If smaller batches are used, this product can be 
		installed with the "dip and roll" method. 
        c. Back roll with a short nap roller.  
        d. Allow primer to 
        cure 8-12 hours (at 75 degrees F) prior to topcoating. A fast cure formulation 
        is available to reduce re-coat window to 4-6 hours. If primer is to be allowed 
        to sit for longer than 24 hours, sand primer before topcoating.  
        B. 
		Product #2 High Build Chemical Resistant Epoxy Floor Coating Topcoat  
        1. Mixing Product #2 High Build Epoxy Floor Coating  
        a. Stir each component prior to mixing.  
        b. Mix two (2) 
        parts by volume of Part A (Base) with one (1) part by volume of Part B 
        (Hardener) for three minutes with a low speed electric drill mixing paddle. 
		Add optional Epoxy.com Anti-Skid fine at a rate of 8-12 volume ounces 
		per gallon of mixed epoxy and mix until well dispersed (typically 1 
		minute). 
        c. 
        Mix only the amount of material that can be immediately poured out.  
        2. 
        Application  
        a. Immediately pour mixed material onto floor in strips and spread 
        at a rate of 160- 200 ft sq. : per gallon with a squeegee. If smaller batches 
		are used, this product can be installed with the "dip and roll" method. 
        b. Back roll immediately 
        with a short to medium nap roller. Do not backroll excessively. 
        3. Allow to cure 
        overnight or a minimum of 12 to 16 hours at 75 °F.  
        4. Apply second coat the same as step 2. 
        Allow to cure 24 hours for light traffic, 48 hours for heavy traffic.  
		For very hot tires, and chemical exposure wait 5-7 days for full chemical cure. END OF SECTION |